A structural integrity reserve study (SIRS) is on file with the state for this 50-unit community at A1A and Bimini Rd, completed August 21, 2023 by a reserve specialist (DBPR's SIRS database, as of October 5, 2026).
Habitable stories aren't on file. No year built is on file, so we use the declaration year, 1984. If its CO was issued in 1984 and it has three or more habitable stories, its first milestone inspection would have been due by December 31, 2024 (s. 553.899(3)(a), F.S.). Whether it was done is on file with the local building official.
SIRS completed August 21, 2023.
Declaration year; no year built.
Floors not on file.
First inspection would have been due.
Timeline
- 1984Declaration recorded October 2, 1984.
- 2023SIRS completed August 21, 2023; the next is due within 10 years (s. 718.112(2)(g)1., F.S.).
- 2024First milestone inspection would have been due.
Need the next inspection or study priced?
Quote requests for Commodore open once firms serving Brevard County sign on. How requests will work.
Quote requests open soonFacts and sources
| Fact | Value | Source |
|---|---|---|
| Units | 50 in 2 buildings | DBPR condo file, Oct 3, 2026; building report |
| Declaration recorded | October 2, 1984 | DBPR condo file, Oct 3, 2026 |
| Units per building | 50, 50 | SB 4-D report, Oct 5, 2026 |
| SIRS completed | August 21, 2023, by a reserve specialist | DBPR SIRS database, Oct 5, 2026 |
| DBPR project number | PR1P010424 | DBPR condo file, Oct 3, 2026 |
| Building addresses | 1700 Commodore Blvd (50); 1750 Commodore Blvd (50) | SB 4-D report, Oct 5, 2026 |
Owners
Owners can ask the board for Commodore's inspection summary, if one was done, and the August 21, 2023 SIRS (s. 553.899(9) and s. 718.112(2)(g)11., F.S.).
Cocoa Bch comparison
Cocoa Bch has 3 condo communities with 25+ units declared or built before 1997. DBPR's SIRS database lists a study for at least 2 of them (67%).
Nearby condos
FAQ
Does Commodore in Cocoa Bch need a milestone inspection?
Only if it has three or more habitable stories, which our records don't show.
Has Commodore filed its SIRS?
DBPR lists a Commodore study completed August 21, 2023.
Corrections: condoduedate@agentmail.to · Deadline calculator