A structural integrity reserve study (SIRS) is on file with the state for this 156-unit community at 2601 Southwest Archer Rd, completed June 25, 2024 by an engineer (DBPR's SIRS database, as of October 5, 2026).
The association reports 3 floors and a 1993 construction year. If its certificate of occupancy (CO) was issued in 1993 and all 3 floors are habitable stories, its first milestone inspection would have been due by December 31, 2025 (s. 553.899(3)(a), F.S.). Whether it was done is on file with the local building official.
SIRS completed June 25, 2024.
Year built (county roll).
Floors (SIRS filing).
First inspection would have been due.
Timeline
- 2006Declaration recorded August 30, 2006.
- 2024SIRS completed June 25, 2024; the next is due within 10 years (s. 718.112(2)(g)1., F.S.).
- 2025First milestone inspection would have been due.
Need the next inspection or study priced?
Quote requests for University Commons open once firms serving Alachua County sign on. How requests will work.
Quote requests open soonFacts and sources
| Fact | Value | Source |
|---|---|---|
| Units | 156 | DBPR condo file, Oct 3, 2026 |
| Declaration recorded | August 30, 2006 | DBPR condo file, Oct 3, 2026 |
| Year built | 1993 | Alachua property roll (1993); association's SIRS filing (1993) |
| Floors | 3 | SIRS filing, self-reported |
| SIRS completed | June 25, 2024, by an engineer | DBPR SIRS database, Oct 5, 2026 |
| DBPR project number | PR74134 | DBPR condo file, Oct 3, 2026 |
| FEMA flood zone | X, minimal flood hazard | FEMA flood layer, Oct 5, 2026 |
| Unit parcels | 156 on the county roll, averaging 1,150 sq ft of living area | Alachua property roll 2026 |
| Distance to the coastline | about 39 miles | Our calculation, TIGER 2024 |
Owners
Owners can ask the board for University Commons's inspection summary, if one was done, and the June 25, 2024 SIRS (s. 553.899(9) and s. 718.112(2)(g)11., F.S.).
Gainesville comparison
University Commons is older than 57% and larger than 80% of Gainesville's 76 communities with 25+ units (our calculation from the DBPR condo file, Oct 3, 2026).
Nearby condos
All Gainesville condo communities · Alachua County condo communities
FAQ
Does University Commons in Gainesville need a milestone inspection?
Yes, at 30 years from its certificate of occupancy, if it has three or more habitable stories; its SIRS filing reports 3 floors.
Has University Commons filed its SIRS?
DBPR lists a University Commons study completed June 25, 2024.
Corrections: condoduedate@agentmail.to · Deadline calculator